Updates


Nimitz & Rosecrans Roadway Improvements Complete

We are pleased to announced that work has been completed on the Nimitz & Rosecrans Roadway Improvement Project! The new dual left-hand turn lanes in both directions are completed, new bike lanes have been installed, and the storm water system in the area has been significantly improved. (The project is….Read More



Paving complete

After a few rain delays, paving on Rosecrans has been completed. We appreciate you patience as we worked to accomplish this milestone! Remaining activity on the project includes pouring and stamping concrete in the medians, installation of traffic loops (in-road traffic sensors), and roadway striping. We’ll post updates as these items….Read More



Paving halfway complete

Paving on Rosecrans has been halfway completed. The remainder of the paving was scheduled for this week, but has had to be postponed due to rain in the forecast. We will report the new date for the completion of paving as soon as it is determined.



Paving on Rosecrans postponed

Due to rain in the weather forecast, paving on Rosecrans has been postponed. It is tentatively scheduled to begin on March 14, weather permitting.



Paving on Rosecrans to occur this week

As the Nimitz-Rosecrans Roadway Improvement Project nears its completion, construction crews will soon be paving segments of the roadway and intersection. This work is currently scheduled to occur on March 6 and March 7 between the hours of 8 p.m. and 5 a.m. (weather permitting). Traffic control measures will be….Read More



Final Phase Underway

Work is underway on the final phase of the Nimitz-Rosecrans Roadway Improvement Project. This phase consists of reconfiguring medians on Rosecrans and Nimitz and most work will be done at night to minimize traffic impacts during the day. Crews will start working on the medians on Nimitz on either side of Rosecrans…..Read More



WORK BEGINS ON FINAL PHASE OF NIMITZ-ROSECRANS ROADWAY IMPROVEMENT PROJECT

Construction crews will begin work on the fourth and final phase of the Nimitz-Rosecrans Roadway Improvement Project on November 19. The completion of the second and third phases saw the construction of new traffic lanes; sidewalks, curbs, and gutters; the relocation of traffic lights and street lights; and the installation….Read More



Construction Update

While it may appear that there hasn’t been much occurring at the northwest corner of Nimitz and Rosecrans, a lot has been accomplished, but most work has been underground. Construction crews have been hard at work relocating utilities, relocating street and traffic lights, and installing a new modular wetland to….Read More



Work on Southbound Side of Rosecrans Nears Completion

Work on the southbound side of Rosecrans Avenue and on Nimitz Boulevard at Rosecrans is nearing completion. An unanticipated and unknown underground condition in the field caused a delay in work, but this has been resolved and crews are working to wrap-up work in this area over the next several….Read More



Intermittent Nighttime Construction

In order to relieve traffic impacts on Rosecrans during the day, some intermittent nighttime work will occur on the project during the period from August 27 through November 30. Work during this phase includes demolition, concrete pouring, and asphalt paving to accommodate an additional left-hand turn lane and dedicated right-turn….Read More